Late certificate payments: what a contractor can do

A certificate is paid late when the payment period set by the contract or the law passes without the contractor being paid the approved amount. In Egyptian public contracts, works certificates are paid within 60 days of submitting them complete; under FIDIC 2017, within 56 days by default of the Engineer receiving the Statement. Under both, the contractor is entitled to a financing cost for the delay, on conditions each one sets.

By Ta3mir engineering team · Published · Last updated

Payment periods and compensation for delay under both references

Egyptian public contracts (Law 182 and its Regulation)FIDIC Red Book 2017
Approval periodThe public body reviews the certificate and pays what it approves within 60 days of the complete certificate being submitted (art. 45)The Engineer issues the Interim Payment Certificate within 28 days of receiving the Statement (14.6)
Payment periodWithin the same 60 days56 days by default from the Engineer's receipt of the Statement, not from the certificate (14.7)
What is paid95% of the value of work done and 75% of materials delivered to site after a count (Regulation art. 93)What the certificate approves after retention and deductions; amounts may be withheld only for listed reasons (14.6)
Compensation for delayThe financing cost for the delay at the credit and discount rate the Central Bank announces at the time of accounting, against official documents of the amount (art. 45)Financing charges compounded monthly at the prime short-term lending rate plus 3 percentage points a year unless the Contract Data says otherwise, payable on request (14.8)
If the certificate is refusedIt may be sent by express mail through the National Postal Authority; the period runs from its postal receipt (art. 45)Notices and Statements take effect when received in the way the contract sets (1.3)
Price adjustmentReviewed and paid within 60 days of the claim, and the certificate is not held for it (Regulation art. 97)Per the cost indexation schedule if the contract has one (13.7)

These are the two references as summarised in Ta3mir's reference data. The published law and Regulation and your contract's particular conditions govern, and your contract's periods may differ.

Why certificates are usually paid late

  • An incomplete certificate: the payment period only starts once it is submitted complete.
  • Disputed quantities because measurement sheets or approved inspection records are missing.
  • Additional work or variations not yet approved, included in the certificate ahead of approval.
  • Slow review by the consultant or the public body, or funds not yet available.
  • Arithmetic errors, or a «previous» column that does not match what was actually approved last time.

Under FIDIC 2017 the Engineer may withhold a payment certificate or amounts in it only for listed reasons: an amount below the minimum in the Contract Data, defective work, unperformed obligations or significant errors (sub-clause 14.6). Knowing them helps you prepare a certificate the reviewer has no reason to hold back.

In Egyptian public contracts (Law 182)

  1. Submit the certificate with all its documents and get proof of the date received, since the 60 days run from it (art. 45).
  2. If the public body refuses a complete certificate, send it by express mail through the National Postal Authority and keep the posting receipt and proof of delivery (art. 45).
  3. Follow up the review in writing within the period, and ask for any comment on quantities or documents so you can fix it early.
  4. If payment is late, claim the financing cost for the delay with official documents of the amount, as the law requires, and confirm with the public body which document it accepts (art. 45 and Regulation art. 93).
  5. Submit price adjustment as a separate claim: it is paid within 60 days of submission, and the approved certificate may not be held for it (Regulation art. 97).
  6. After completion, if the public body fails to take over the works you may ask for a neutral committee formed within 7 days, whose report within 30 days of its formation binds both parties (Regulation art. 99); provisional taking-over is when retention is paid.

Under the FIDIC Red Book 2017

  1. Financing charges: they run on the unpaid amount from the end of the payment period, whatever the date the certificate was issued, and the contractor requests them without a Notice of Claim (sub-clause 14.8).
  2. Evidence of finance: sub-clause 2.4 sets when the contractor may ask for reasonable evidence of the employer's financial arrangements, which the employer must provide within 28 days of the request.
  3. Suspension or slowing down: if the certificate is not issued or payment is not made on time, the contractor may suspend or slow down work no less than 21 days after giving Notice, and is entitled to an extension, cost plus profit and financing charges (sub-clause 16.1).
  4. Termination: no certificate within 56 days of the Statement, or no payment within 42 days after the payment period expires, are grounds for a Notice of termination, with 14 days for the employer to remedy the matter (sub-clause 16.2). It is a major decision; do not take it without a contracts adviser.

These periods and rates are defaults in the General Conditions; the Contract Data may change the payment period and the financing rate. The full payment cycle is in the FIDIC Red Book 2017 guide.

The documents that protect your entitlement

DocumentWhy you need it
Proof of the date the certificate or Statement was receivedThe payment period and the days late run from it
Measurement sheets and inspection recordsThey prevent the quantity disputes that hold up approval
Approved variation ordersThey prove the additional work in the certificate is approved
Written correspondence and NoticesThey prove the follow-up and its dates; under FIDIC nothing else replaces a Notice
Official documents of the financing cost amountRequired to claim the financing cost under Law 182

Worked example: the financing cost on a late certificate

Illustrative figures in an Egyptian public contract, at the 19.5% credit and discount rate the Central Bank of Egypt kept at its 24 September 2026 Monetary Policy Committee meeting. The applicable rate is the one announced at the time of accounting; the calculation here is simple, not compounded, on a 365-day year, an assumption for illustration only.

ItemValue
Approved certificate value (EGP)1,000,000
Date the complete certificate was submitted1 February 2026
Latest payment date (60 days)2 April 2026
Actual payment date1 June 2026
Days late60
Credit and discount rate (Central Bank of Egypt, decision of 24 September 2026)19.5%
Financing cost = value × rate × days ÷ 365 (EGP)32,054.79

The certificate was submitted on 1 February 2026, so the latest payment date is 2 April 2026; it was paid on 1 June 2026, 60 days late, so the financing cost in this example is EGP 32,054.79. It is claimed with official documents of the amount, and the figure is reviewed with the public body.

A contractor's steps when a certificate is paid late

  1. Check the payment period in your contract and when it starts: submission of the complete certificate, or the Engineer's receipt of the Statement.
  2. Work out the deadline for each certificate and log it in a follow-up sheet.
  3. Send a written reminder as the deadline nears, and a formal letter or Notice of the delay once it has passed.
  4. Prepare the documents the reference requires to claim the financing cost, and work it out on the actual days late.
  5. Under FIDIC, if the delay continues, review with a contracts adviser the option to suspend after at least 21 days' Notice.
  6. Keep submitting later certificates on time: one late payment does not stop the others' periods.

How to do it in Ta3mir

In Ta3mir a certificate goes through an approval path including the consultant, and once approved you issue a claim with a due date and follow its collection.

  • A claim from the approved certificate with a due date, its collection shown in receivables ageing.
  • Certificate items as previous, current and cumulative, so «previous» always matches what was approved.
  • Approved variation orders adjust the contract value, with a register of contractual claims per project.
  • The in-app contracts reference summarises the FIDIC Red Book 2017 and Law 182 with its Regulation, with their time limits.

Sources

This guide is an explanatory summary written by the Ta3mir engineering team. It is not the text of the law or of any contract and it is not legal advice. Figures in the examples are illustrative. Your contract and the officially published text govern, so check them with a contracts adviser before acting.