Item price-analysis template in Excel
A free Excel sheet to analyse the price of any construction item, with no sign-up. You type how much of each material, labour and equipment one unit of the item uses and its price; the file adds up the direct cost, then overheads and profit, and gives the unit price.
Free, with no sign-up and no email · Excel file (xlsx) in Arabic, right-to-left, ready to print
When do you need a price analysis?
- Before pricing a tender BOQ: to know the unit price covers its cost and your margin.
- When the consultant or the owner asks for the analysis of a new item or a variation item.
- When material prices rise: to see how steel or cement prices move each item.
- To compare a subcontractor quote with the real cost of the item.
What is in the file?
- One right-to-left sheet, set to print on A4 landscape.
- Two fully analysed example items (reinforced concrete slab, brick wall) and a third empty item with its formulas to copy for your own items.
- Per item: material, labour and equipment lines, the direct cost, overheads, profit and the unit price.
- The rates and prices in the two example items are for illustration only, not market prices.
How to fill it, step by step
- Type the item name and unit in the item title line (the coloured line).
- Add the material lines with what one unit of the item consumes, waste included.
- Add labour (piece rate, or day rate converted to the item unit) and equipment or wear and tear.
- Check the overheads and profit percentages in the quantity column against your company costs and the project.
- Copy the whole empty item for each new item; the formulas come with it.
Column guide: what goes in each column
| Column in the file | What to write |
|---|---|
| النوعType | Materials, labour or equipment. The split helps when reviewing each cost type. |
| البيانDescription | The material, labour or equipment name. |
| الوحدةUnit | The unit you buy or pay it in: tonne, m3, number, day... |
| الكمية لوحدة البندQuantity per item unit | How much of it one unit of the item uses, waste included. |
| سعر الوحدةUnit price | The current purchase price or wage in your area. |
| التكلفةCostformula | Quantity × price. A formula, do not type in it. |
| المصدر والملاحظاتSource and notes | Where the price comes from and its date (supplier quote, price bulletin, past invoice). |
Worked example: one m3 of reinforced concrete slab
With the example rates and prices in the file (illustration only):
| Materials | 5,595.40 |
|---|---|
| Labour | 900.00 |
| Equipment | 320.00 |
| Direct cost | 6,815.40 |
| Overheads 10% of direct | 681.54 |
| Profit 10% on direct plus overheads | 749.69 |
| Unit price | 8,246.63 |
Profit is taken on the direct cost plus overheads, the same way Ta3mir prices an estimate.
Practical notes
- Put waste in the consumption rate, not in the price, so the price matches the supplier quote.
- Update steel and cement prices before every tender; they move concrete item prices the most.
- Note each price's source and date; the consultant asks for it when reviewing a new item analysis.