Daily site report template for site engineers

A daily site report on one printable Excel sheet, free and with no sign-up. It records what happened on site today: who came, which equipment worked, what was done, what materials arrived and what held the work up.

Free, with no sign-up and no email · Excel file (xlsx) in Arabic, right-to-left, ready to print

Why write a daily site report?

  • A written record of labour and equipment to go back to for daily wages and subcontractor checks.
  • Evidence of delay causes (power cuts, weather, waiting for approval) to support an extension of time request.
  • Daily quantities done, so the certificate take-off is faster and more accurate.
  • Materials received with their delivery note numbers, before the supplier invoices arrive.

What is in the file?

  • One right-to-left sheet, set to print on A4 portrait.
  • The day details at the top, then six tables: labour, equipment, work done, materials received, delays and obstacles, and visits and instructions.
  • One or two example lines per table marked «مثال», and automatic totals for the labour count and delay hours.
  • Space for general notes and signature boxes for the site engineer, the project manager and the consultant.

How to fill it, step by step

  1. Fill the day details at the top: project, date, weather and temperature, working hours.
  2. Delete the example lines and record the labour present, one line per trade and subcontractor.
  3. Record the equipment with working hours, idle hours and the idle reason.
  4. Write the work done today with quantities and location, and the materials received with their delivery note numbers.
  5. Never leave a delay without its cause, duration and responsible party, or a visit without its instructions.
  6. Print and sign the report, ask the consultant to sign if the contract requires it, and file it with the day's photos.

Column guide: what goes in each column

Labour

Column in the fileWhat to write
مNo.Line number.
المهنة أو الفئةTradeCarpenter, steel fixer, mason, labourer... one line per trade.
مقاول الباطنSubcontractorWho the workers belong to, or «المقاول» (the contractor) for your own crew.
العددHeadcountThe number of workers actually present.
ساعات العملWorking hoursHours worked per worker today.
مكان العمل أو البندLocation or itemWhere they worked or on which item.
ملاحظاتNotesAnything that helps whoever reads the report later.

Equipment

Column in the fileWhat to write
مNo.Line number.
المعدةEquipmentType: mixer, vibrator, hoist, loader, concrete pump...
المالك أو الموردOwner or supplierThe contractor's own, or the rental company.
العددUnitsNumber of units on site.
ساعات التشغيلWorking hoursHours the equipment actually worked.
ساعات التوقفIdle hoursHours on site without working. They matter for rental charges.
سبب التوقفIdle reasonBreakdown, waiting for materials, waiting for approval...

Work done

Column in the fileWhat to write
مNo.Line number.
البند أو النشاطItem or activityThe item name as in the BOQ or the schedule.
المكانLocationFloor and grid lines, or the part of the building.
الوحدةUnitm3, m2, linear metre, tonne, number.
الكمية المنفذة اليومQuantity done todayOnly what was done today, not the cumulative.
نسبة الإنجاز التراكميةCumulative progressEstimated share of the item complete by the end of the day.
ملاحظاتNotesAnything that helps whoever reads the report later.

Materials received

Column in the fileWhat to write
مNo.Line number.
المادةMaterialThe material and a short specification.
الموردSupplierWho supplied it.
الوحدةUnitTonne, m3, number, roll...
الكميةQuantityThe quantity actually received after counting or weighing.
رقم إذن الاستلامDelivery note no.The delivery note or waybill number, to match against the invoice.
الفحص والملاحظاتInspection and notesAccepted or rejected, and any samples taken for testing.

Delays and obstacles

Column in the fileWhat to write
مNo.Line number.
السببCauseWhat stopped or slowed the work.
المدة بالساعاتDuration (hours)How long it lasted. The file totals it under the table.
الأعمال المتأثرةWorks affectedThe items or activities held up.
الجهة المسؤولةResponsible partyOwner, consultant, contractor or an outside party.
الإجراء المتخذAction takenWhat you did to limit the impact.
ملاحظاتNotesAnything that helps whoever reads the report later.

Visits and instructions

Column in the fileWhat to write
مNo.Line number.
الزائرVisitorThe visitor's role or name.
الجهةOrganisationOwner, consultant, a public authority...
الوقتTimeTime of the visit.
الغرضPurposeInspection, handover, meeting...
التعليماتInstructionsWhat was asked, in writing or verbally. Verbal instructions need written confirmation later.
ملاحظاتNotesAnything that helps whoever reads the report later.

Example: a slab pour day

The first-floor slab pour, as in the example lines inside the file:

Labour8 carpenters and 6 steel fixers, 8 hours
EquipmentA mixer idle for 2 hours waiting for gravel, and two vibrators
Work done42 m3 of first-floor slab concrete
Delay2-hour power cut, standby generator started
VisitsThe consultant approved the pour after the rebar cover was fixed

A month later, these lines are what proves why the work stopped for two hours and who approved the pour.

Practical notes

  • Write the report the same day; a report written a week later carries little weight in a claim.
  • Record idle hours of rented equipment apart from its working hours.
  • File the day's photos under the report number and date.

Log the day from site in Ta3mir