Certificates & contracts

Payment certificates and contracts, from measurement to the final certificate

Interim and final certificates for owner and subcontractors, approved by the consultant, with retention, deductions, variation orders, invoices, Excel import.

Ta3mir screenshot: the register of owner and subcontractor certificates, interim and final

What is Certificates & contracts in Ta3mir?

Interim and final certificates for the owner and for subcontractors: previous and current quantities summed cumulatively, retention and deductions at the foot of the certificate, an approval path through the consultant, then a claim and an invoice from the approved certificate, and a contract register showing each value after approved variation orders.

Certificate items: previous, current, cumulative

Enter only this period's quantities; they add to the previous ones automatically to show the total, its value and the payment percentage per item, with ordinary and additional works kept apart.

Ta3mir screenshot: certificate items with previous, current and total quantities

Subcontractors and their certificates

Each subcontractor with its contract, certificates and account statement, so you know what is approved, paid and outstanding.

Ta3mir screenshot: the subcontractor register with their certificates

An invoice from the approved certificate

Once a certificate is approved, raise a claim with a due date and follow its collection in receivables ageing.

Ta3mir screenshot: invoices issued from approved certificates

From the contractor's Excel to a certificate

Upload the contractor's certificate workbook and match each line to a BOQ item before saving, so nothing enters the BOQ without an engineer's review.

Ta3mir screenshot: importing a contractor certificate from Excel and matching its lines to the BOQ

Features in Certificates & contracts

From certificate items to the variation order and the invoice,
here is what is inside:

Ta3mir screenshot: certificate details
Ta3mir screenshot: a variation order
Ta3mir screenshot: invoices issued from certificates

Perks of Certificates & contracts

The whole certificate cycle, from measurement to the final account, in one place with numbers that never disagree.

Approval with segregation of duties

Every certificate follows an approval path that includes the consultant, and no one approves a certificate they prepared.

Retention and deductions

Retention and deductions to date at the foot of every certificate, and retention release by a recorded decision.

Variation orders and claims

Approved variation orders adjust the contract value, and a contractual claims register is kept for every project.

Next certificate from the last one

Copies the last certificate's items and moves its totals into the previous column in one click.

Period closing and final certificates

A closing wizard lists drafts, retention and expired guarantees before preparing final certificates, then a closing report for the project.

Arabic print and CSV export

A print-ready certificate in a professional Arabic layout, and CSV export of its items and values.

  • Payment certificates & contracts
  • Technical office & documents
  • Accounting
  • Scheduling & planning
  • Take-offs & BOQ
  • HR, attendance & payroll
  • Cost control
  • Procurement, stores & equipment
  • Site management & daily logs