Subcontractor payment certificate template in Excel

A subcontractor certificate is what the main contractor pays a subcontractor for the period works. This free Excel template needs no sign-up: the same previous, current and cumulative logic, with the deductions of a subcontract, including the materials the main contractor supplied.

Free, with no sign-up and no email · Excel file (xlsx) in Arabic, right-to-left, ready to print

Who is this template for?

  • Main contractor: prepare each subcontractor's certificate and check its quantities before paying.
  • Subcontractor: claim the period works from the main contractor on the same table it will be checked on.
  • Project manager: compare what is paid to subcontractors with what is claimed from the owner for the same items.
  • Accountant: see the net due after the materials supplied and the retention are deducted.

What is in the file?

  • One right-to-left sheet, set to print on A4 landscape.
  • The subcontract details in the title: project, main contractor, subcontractor, subcontract number and trade.
  • Two item sections, subcontract works and additional works, with example items marked «مثال» and empty rows with their formulas.
  • The deductions: retention, advance recovery, materials supplied by the main contractor, delay penalties (an optional line) and other deductions, then the net due and the signature boxes.

How to fill it, step by step

  1. Type the project, main contractor, subcontractor, subcontract number, certificate number and period in the title lines.
  2. Delete the example items and copy the subcontract items with their rates and quantities, not the owner contract items.
  3. Copy the cumulative quantity of the last approved subcontractor certificate into «الكمية السابقة» (previous quantity), and type the period quantity in «الكمية الحالية» (current quantity).
  4. Type the value of the materials you supplied to the subcontractor as a negative on its line: what was deducted before under previous, this period's materials under current.
  5. Leave the delay penalties line at zero unless the subcontract sets a penalty and the delay is established.
  6. Check the retention and advance rates against the subcontract, then write the amount due in words and collect the signatures.

Column guide: what goes in each column

Column in the fileWhat to write
مNo.The item number as in the subcontract.
بيان الأعمالDescription of worksThe item description as in the subcontract bill of quantities.
الوحدةUnitUnit of measure: m3, m2, linear metre, tonne, number or lump sum.
الكمية التعاقديةContract quantityThe item quantity in the subcontract, not in the owner contract.
الفئةUnit rateThe rate per unit in the subcontract.
الكمية السابقةPrevious quantityThe cumulative quantity of the last approved subcontractor certificate. Zero on the first.
الكمية الحاليةCurrent quantityWhat the subcontractor did in the period, from a take-off the site engineer checks.
الكمية الإجماليةCumulative quantityformulaPrevious + current. A formula, do not type in it.
نسبة الصرف %Payment %100% for a finished item, a lower share for an item not yet accepted or waiting for snags to be fixed.
القيمة السابقةPrevious valueformulaPrevious quantity × rate × payment %.
القيمة الحاليةCurrent valueformulaCurrent quantity × rate × payment %.
القيمة الإجماليةCumulative valueformulaCumulative quantity × rate × payment %.
نسبة الإنجازProgressformulaCumulative ÷ contract quantity. Above 100% needs a variation to the subcontract.
ملاحظاتNotesThe take-off record number, or why the payment % is reduced.

A worked example from the file

The internal plaster item: contract quantity 6,500 m2 at a rate of 115, 1,200 m2 paid before and 1,800 m2 done this period, so the current value is 207,000. For the whole certificate (the five example items):

Works this period573,500
Retention 5% on the period works28,675
Advance recovery 10% on the period works57,350
Materials supplied by the main contractor this period62,500
Delay penalties0
Net due to the subcontractor for this certificate424,975

Net due for the certificate = net to date minus the net of the previous certificates; the file works it out on the last line of the summary.

Practical notes

  • Record every material issue to a subcontractor on an issue note it signs; deducting materials without one invites a dispute.
  • The retention and advance rates in the file are examples; the right rates are the ones in the subcontract.
  • Do not pay a subcontractor more quantity than the consultant approved for the owner on the same item, unless there is a written reason.
  • If the contract adds a tax or a stamp duty, put it on the other deductions line as a negative.