Quantity take-off: from the drawings to the bill of quantities

Quantity take-off is working out the quantity of each work item from the drawings and specification in its unit of measurement, such as cubic metres of concrete, square metres of masonry or tonnes of reinforcing steel. Measurements are recorded in a measurement sheet showing the count and dimensions for each item, then totalled in the bill of quantities, which is priced and becomes the basis of the tender, the budget and the payment certificates.

By Ta3mir engineering team · Published · Last updated

Kinds of take-off and what they produce

Take-off for pricingTake-off for a certificate
SourceDrawings and specification, before constructionWork actually done on site
PurposePrepare the bill of quantities, price the tender and set the budgetProve the quantities done in each certificate
Prepared byThe contractor's technical office or the consultantThe site engineer, checked by the consultant
OutputA measurement sheet and a bill of quantitiesA measurement sheet for the period, attached to the certificate

Either way, every figure in the bill must trace back to a line in the measurement sheet, and every line to a drawing and a location. That is what makes a quantity checkable at approval or in a dispute.

How a bill of quantities is laid out

ColumnWhat it holds
Item no.Numbered by work section, such as earthworks, then concrete, then masonry, then finishes
DescriptionThe work, materials and specification it covers; the rate covers everything the description says
UnitThe agreed unit of measurement for the item
QuantityThe net figure from the measurement sheet
Unit rateThe rate from the rate analysis
AmountQuantity × unit rate, then section totals and the grand total

In remeasurement contracts the bill quantities are estimates, and the contractor is paid for the quantities actually measured (sub-clauses 1.1 and 12.3 of the FIDIC Red Book 2017). The method of measurement is the one in the Contract Data or consistent with the bill, measuring the net actual quantity of each item with no allowance for bulking or waste unless the contract says otherwise (sub-clause 12.2).

Common units of measurement

WorkCommon unit
Excavation and backfillCubic metre (m³)
Plain and reinforced concreteCubic metre (m³)
Reinforcing steelTonne or kilogram
MasonrySquare metre (m²), or cubic metre per the contract
Waterproofing, plaster, paint and tilesSquare metre (m²)
Skirting, pipes and cablesLinear metre (m)
Doors, windows and sanitary fittingsNumber, or square metre for windows per the contract

These are common units in practice. The binding unit is the one written against the item in your contract's bill of quantities, so do not change it when measuring.

The order and rules of measurement

  1. Start from the list of items in the specification so none is missed, then measure in construction order: earthworks, blinding, foundations, waterproofing, backfill, columns and slabs, masonry, finishes, then electromechanical work.
  2. Use the dimensions written on the drawing; do not scale off a printed drawing.
  3. Record each measurement on its own line: location or grid line, count, length, width and height.
  4. Follow a fixed direction on each plan, such as clockwise from a given grid line, so no element is counted twice or missed.
  5. Deduct openings from masonry and finishes as the contract's method of measurement says.
  6. Total the measurement sheet for each item and carry the net figure to the bill in the same unit.

Common take-off errors

  • Double counting at intersections, such as measuring column concrete inside a beam or slab twice.
  • Forgetting to deduct openings from masonry, plaster and paint, or deducting small openings the method of measurement excludes.
  • Adding a waste allowance to the bill quantity; where measurement is net, waste belongs in the unit rate analysis.
  • Mixing units, such as measuring masonry in square metres and pricing it per cubic metre.
  • Measuring from an unapproved or superseded drawing without recording its number and revision.
  • An item in the description with no line in the measurement sheet, or a line with no location to check.

Worked example: a measurement sheet and four priced items

Illustrative dimensions and rates. A small building with 6 isolated footings under 6 columns, and brick walls 40 m long and 3.00 m high, with 2 doors (1.00 × 2.20) and 4 windows (1.50 × 1.20).

ItemCount × dimensions (m)QuantityUnit rate (EGP)Amount (EGP)
Plain concrete blinding under footings6 × 2.20 × 2.20 × 0.102.904 m³1,8005,227.2
Reinforced concrete footings6 × 2.00 × 2.00 × 0.5012 m³4,50054,000
Reinforced concrete columns6 × 0.30 × 0.60 × 3.003.24 m³5,20016,848
Brick walls less openings40.00 × 3.00 − 11.60108.4 m²45048,780
Total124,855.2

The gross wall area is 120 m² and the openings 11.6 m² (4.4 for doors and 7.2 for windows), so the net is 108.4 m². Note that reinforcing steel is not in this example: it is measured as its own item in tonnes from the reinforcement details, or included in the reinforced concrete rate if the item description says so.

Steps for a quantity take-off

  1. Gather the latest approved drawings, the specification and the contract's method of measurement.
  2. List the items and their units before you start, grouped by work section.
  3. Measure in construction order on a measurement sheet: one line per measurement, with its location and dimensions.
  4. Deduct openings and check intersections so no element is counted twice.
  5. Carry each item's net quantity to the bill and price it from the rate analysis.
  6. Have another engineer check the take-off before the bill is approved, then freeze the approved version.

How to do it in Ta3mir

In Ta3mir you do the take-off, the measurement sheets and the project bill of quantities in one place, with totals summed automatically.

  • Measurement sheets with length, width and height per measurement, for a documented quantity checked item by item.
  • Eight take-off calculators for footings, columns, slabs, rebar, brick, plaster, paint and tiles, with results pushed into the bill.
  • Several bills per project with their status; approval freezes quantities and rates as the project budget base.
  • Import a bill from Excel and review it before saving, and export it to Excel, CSV or PDF.

Sources

This guide is an explanatory summary written by the Ta3mir engineering team and is not the text of any contract or specification. Dimensions and rates in the example are illustrative. The method of measurement and item units in your contract and its bill of quantities govern.